AAA Server Deployment Timeline: What to Expect
A carrier-grade AAA server deployment timeline runs five phases: planning (2–4 weeks), staging and integration (2–3 weeks), pilot (2–4 weeks), cutover (about a week), and post-go-live stabilization (2–4 weeks), for a typical total of 9–16 weeks. Subscriber scale, protocol scope, integration count, and migration versus greenfield decide where in that range a project lands. Pilot […]